NCDRC directs refund of homebuyers’ money
The Hindu
The National Consumer Disputes Redressal Commission (NCDRC) has ordered the developers of ‘Gold Souk Golf Links’ housing project in Sector-17, Sohna, Haryana, to fully refund the payments made by 20 homebuyers as it failed to complete the construction despite the promise of possession in June 2019.
The consumer court noted that the developers has not given any material to establish that the completion of construction and offer of possession was delayed due to force majeure or reasons beyond their control.