Steps to shift VSSC’s massive cargo from Kollam to Thumba
The Hindu
Hydraulic-axle trailer to move at 10 km a day
Arrangements are being made for the smooth transportation of a massive settling chamber for the trisonic wind tunnel being constructed at the Vikram Sarabhai Space Centre (VSSC) at Thumba here from the Kollam port. The settling chamber for the wind tunnel was brought in two sections of 128 tonnes and 57 tonnes to Kollam from Mumbai. They will be moved to Thumba over seven days by road — at the rate of 10 km a day — on a hydraulic-axle trailer.More Related News