India may need up to 28W of additional coal-based power generation capacity by 2032: CEA
The Hindu
“It is seen that apart from under construction coal-based capacity of 25GW, the additional coal-based capacity required till 2031-32 may vary from 17 GW to around 28 GW,” CEA said in a draft national electricity plan
India may need additional up to 28GW of coal-fired power generation capacity by 2032 apart from the 25GW thermal projects that are under construction, said a report by advisory body Central Electricity Authority (CEA).
“It is seen that apart from under construction coal-based capacity of 25GW, the additional coal-based capacity required till 2031-32 may vary from 17 GW to around 28 GW,” CEA said in a draft national electricity plan.
The CEA has put up the ‘Draft National Electricity Plan (Vol-I Generation)‘ for feedback of stakeholders on September 8, 2022.
As per the Electricity Act, 2003, CEA has to prepare the National Electricity Plan once in five years. The Act stipulates that CEA, while preparing the National Electricity Plan (NEP), shall publish the draft and invite suggestions and objections thereon from licensees, generating companies and the public. The inputs on the draft can be given latest by December 5, 2022.
It is also seen that the BESS (Battery Energy Storage System) requirement in 2031-32 is varying from 51GW to 84GW, stated the document.
It also said that in the event of delay in achievement of hydro-based plants, which are in concurred/under construction stage, there is additional requirement of coal of around 4 GW in capacity mix in 2026-27.
In the event of non-availability of the base load nuclear capacity, the (study) model opts for cheaper coal candidates available to provide base load support, it explained.