Unionized workers with the City of Yellowknife were still on picket lines Wednesday, but a court injunction has restricted their strike action.
Justice Andrew Mahar of the Northwest Territories Supreme Court granted an order Tuesday that prevents Union of Northern Workers members from obstructing access to sites where the city operates for 10 days.
That includes the public pool, curling club, solid waste facility, multiplex, field house and city hall.
The order prevents more than six people from picketing at those locations and says any delay to entering those sites should only be to convey information and cannot last more than 10 minutes.
The city filed for the injunction Tuesday claiming wait times for vehicles delayed by picketing workers were increasing and, if not addressed, could cause irreparable harm.
The court order was granted ex parte, meaning it was made without input from the union. According to the city's lawyer, Chris Buchanan, at some point in the next ten days the union and its lawyer will get a chance to weigh in on the injunction.
Lorraine Rousseau, regional executive vice-president of the Public Service Alliance of Canada North, who was in Yellowknife supporting workers on Wednesday, said the unions and striking workers planned to follow the court order.
Chris Aylward, national president of the Public Service Alliance of Canada, who was also in Yellowknife, added that the union plans to fight the injunction.
"What it is is basically an infringement on workers' rights," he said.
"The injunction is not going to stop the strike. We're not going to start taking down picket lines because of the injunction."
Unionized workers went on strike on Feb. 8, hours before a threatened city lockout.
The city and the union, a component of the Public Service Alliance of Canada, began bargaining in May but talks broke down late last year and workers voted to strike last month. Further talks earlier this week failed.
In an affidavit filed in support of the injunction, Kerry Thistle, director of economic development and strategy with the city, wrote that pickets blocking access to city property appeared to be escalating.
Thistle's affidavit included emails from the project manager for Clark Builders, which is constructing Yellowknife's new aquatic centre, to city staff regarding delayed access to the site due to picketing workers. He said the company planned to seek compensation from the city to cover the cost of delays and expressed concern that concrete could become unusable if delayed too long.