'Fudge’ letter, ‘dummy’ invoice and forged document part of WPS HQ paper trail
CBC
Dozens of doctored documents for the Winnipeg police headquarters project were submitted to the city and paid out, including invoices that suggest at least $680,000 was diverted to the construction of a church, according to expert testimony.
Forensic accountant Victor Neufeld spent his third day testifying at the provincial inquiry into the project, detailing how altered documents were used to increase the amount the city paid out to Caspian Projects for the construction of the police headquarters.
Inflated pricing quotes and invoices were used to justify costly change orders on the Graham Avenue building, which ended up costing $214 million instead of the $135 initially approved by city council.
In one example involving painting, Caspian put in a change order which appears to include quotes with inflated amounts, according to Neufeld.
He said the guaranteed maximum price for painting was $2.86 million, but the cost overage change order bumped that up to $2.96M.
“So Caspian is asking for an extra $100,000,” Neufeld said.
When he looked at how the painting budget was used he noticed “inconsistencies.”
“It appears that Caspian said that the $2.86 million was insufficient. They provided those quotations, but at the same time, they did not apparently even use all of that budget for painting.”
Neufeld said masonry, electrical, mechanical and other subcontractors were paid out of that budget.
The Winnipeg Police Service HQ project has been subject to two city-commissioned audits, and a five-year RCMP investigation that resulted in no charges.
Neufeld had access to documents seized by the RCMP from Caspian headquarters as well as investigative files compiled by the RCMP during its investigation.
In an interview with the RCMP, the owner of Abesco, a structural steel subcontractor, expressed remorse for issuing a false invoice at Caspian’s request.
“I should have stopped this,” Wally Fast said. “I wish I could go back in time and change some of the decisions I made.”
Abesco was providing structural steel for both the Winnipeg police headquarters and the Soul Sanctuary church which Caspian was building around the same time.

N.B. Power is in front of the New Brunswick Energy and utilities board seeking approval to raise its rates by 4.75 per cent this year, but the utility's plans to follow that with a 6.5 per cent increase next year and another 6.5 per cent increase the year after have been raising their own set of questions..