Enbridge 'disappointed' as environmental review for Line 5 tunnel extended
BNN Bloomberg
Canadian pipeline giant Enbridge Inc. has been dealt another setback on its Line 5 replacement project in Michigan.
The company said Thursday it was "disappointed" by news that the timeline of a U.S. federal review of Enbridge's proposed $500-million Great Lakes tunnel project has been pushed back by more than a year.
The U.S. Army Corps of Engineers (USACE) said Thursday it now expects to complete its draft environmental impact statement for Enbridge's Line 5 tunnel permit application in spring 2025, rather than late 2023 as earlier indicated.
In an emailed statement, Enbridge spokesman Ryan Duffy said the USACE's decision to extend the permitting process further delays the replacement of the dual pipelines in Michigan's Straits of Mackinac, and will essentially push the start of construction until at least 2026.